When internal projects keep getting pushed back, it's rarely one decision. A firm's own project can slip a week at a time while everyone involved has a good reason.
An internal project rarely falls behind in one bad week. It slips a Thursday at a time, and each Thursday looks like time that can be made up.
Halloran Engineering had run on the same accounting system for eight years. Invoices went out close to three weeks after the end of each month. A PM who wanted to know where a budget stood asked accounting to run a report. Brian Halloran, who owned the firm, wanted invoices out within days of month-end and PMs who could see their own numbers. In April the firm hired an implementation partner and started on a new accounting and project system, with a nine-month plan to a January 1 go-live.
Joan Pruitt, the CFO, ran the project. Over the summer she and Dave Lindqvist, the partner's consultant, set up the accounting side. The system had to work for the project managers too, so Brian asked for the PM the others trusted most, Teresa Ruiz, fourteen years at the firm.
Her director took a couple of smaller projects off her plate, so from September, Thursday mornings were her working sessions with Dave. He needed her help setting up each kind of project to match how the PMs actually ran and billed it. Joan's sign-off on that setup was due October 15. In early November, billing would run draft invoices on a subset of projects for their PMs to review.
In the second week of September, three days before the permit set for Teresa's hospital client was due, the hospital moved an equipment room, so the framing under it had to be redesigned. The next day, Teresa emailed Dave to push their Thursday session.
"I'll make up the time next week," she wrote.
Dave's weekly status report marked the October 15 sign-off at risk, with a note that Teresa expected to make up the time. She made the next session. The week after, the architect's comments on the revision came back, so she pushed again. She made up what she could in the evenings, but most of the setup had to be worked through with Dave.
When Joan asked Teresa's director about the report, the director said the hospital job had two deadlines close together. Teresa would catch up once they were behind her.
At the end-of-September steering meeting, Dave told Brian and Joan that the sign-off was at risk and the plan had little room after it. Teresa, there for the setup, said she'd get through as much as she could before the 15th. Joan asked Dave to have a recovery plan ready in case.
Teresa made the first session in October. The next week, her other client moved a design review up, so that Thursday went to the client.
October 15 came without the sign-off. The next morning, Dave sent the plan. Setup was three sessions behind. Conversion couldn't start until it was signed off. November's test billing, with three PMs already booked to review their drafts, couldn't start until conversion was checked. Keeping January meant making up all three sessions the following week. Otherwise, with year-end and the audit in the way, the next clean date was April 1, with three more months on the old system.
Brian and Joan asked Teresa's director whether her client work could spare her three mornings that week. Both of her jobs had deliverables that week, the director said. Handing either one to another PM that close would cost more than it saved.
So Brian and Joan asked the partner's account manager to price April. Three Thursday mornings that had gone to client work were about to come back as one bill.
When a firm's own project falls behind, a busy year is the easy explanation, and often a true one. In a Gartner survey in July 2024, three-quarters of the HR leaders polled said their managers are overwhelmed by how much their responsibilities have grown. Busy is the backdrop, though. Several different things can be happening in front of it. Often you can hear which one in what people say about the project.
"I'll make up the time next week." When the person an internal project depends on also has client work, that person is often the one deciding, week by week, what gives. Moving a client's date means a conversation with the client, so the internal project's hours tend to be the ones that move. Each trade is a reasonable call, so none of them looks like a decision about the project.
"We cleared room for it." Taking work off someone's plate makes room for an internal project, but that room doesn't always hold once a client deadline lands in it. What happens to the project's time then, and who hears about it, shows whether the room was ever protected.
"It counts against my numbers." At many firms, time on an internal project is charged to overhead, so it lowers the utilization people are reviewed on, and sometimes paid on. The sign is internal work drifting to evenings and weekends, which makes its real cost hard to see.
"Everybody's slammed." Sometimes the people on the project are behind on everything they carry. The project is only one part of it. Ask what would happen if the project stopped tomorrow. If they'd still be behind, protecting the project's hours moves the shortfall somewhere else rather than closing it.
"It's waiting on one person." When the work can't move without one particular person, adding people to that piece doesn't help. Ask who else could do that piece if that person were out for two weeks.
"The date was always tight." Some plans never had enough hours behind them. If every hour that was promised had shown up, would the date have held? If not, the date was the problem before anyone's week was.
From the owner's chair, these can all look like a project that's behind with good people on it. Several can be at work on the same project. Each one is fixed differently.
When a firm's own project starts to slip, no one person sees all of it. The implementation partner's status report shows a milestone at risk. The person the work depends on knows which weeks went to clients and what got made up. Whoever plans client work sees client deadlines. Leadership hears that it's behind and catching up. Each of those is accurate. None of them is the whole picture.
Firms that deliver projects for a living are full of people who are good at recovering a lost week, so a plan to catch up is easy to count on. What a weekly status doesn't show is the running total. Three reasonable weeks can add up to a quarter.
Why do our own projects always come last?
Usually because client work wins each small trade-off, and they add up to more than anyone decided. Moving a client's date means a conversation with the client, so when a week runs short, it's often your own projects that give. Where the person a project depends on also has clients, that person often makes the trade-off. Each one is a reasonable call, so none of them looks like a decision about the project. Other common reasons look the same from outside. Room cleared for the project may not hold once a client deadline lands in it. Internal hours may count against the utilization people are reviewed on. People can be stretched across everything they carry, or the work may wait on one person. Sometimes the date never had enough hours behind it.
Do other firms struggle to get their own projects done?
In our experience, often, though nothing we've found counts how many. The closest measure is about load. In a Gartner survey in July 2024, three-quarters of the HR leaders polled said their managers are overwhelmed by how much their responsibilities have grown. That measured how HR leaders see managers' workloads in general, not internal projects.
Up to thirty minutes, confidential, and an honest read on where your internal project really stands.
Get Your Free Pulse Check →At firms whose work is projects for clients, their own project is often the one that slips, one reasonable trade-off at a time.
More in this cluster →Thirty minutes. Confidential. No card required.